Read this first: Exactly what your application must include is set by your municipality, and the list differs everywhere. Everything below is the common Canadian pattern to help you assemble a complete package and ask the right questions. Confirm the document list with your local building department before you apply — most use a published "permit application checklist."
5–7core documents, typical
~10 daysreview target, houses (ON)
~43%first submissions sent back
2approvals: zoning + code

✓ The Decision — Prepare It Yourself or Get Help?

  • Prepare your own package if: it's a simple, prescriptive Part 9 project on your own home (a deck, a shed, a standard detached garage), you can produce clear scaled drawings, and your municipality accepts owner-prepared drawings.
  • Get a designer or engineer if: the project is structural beyond the code's prescriptive tables (a beam, a load-bearing wall removal, an engineered foundation), large or over three storeys, or the drawings are beyond what you can produce accurately.
  • Confirm the checklist before you draw anything — the municipality's application checklist tells you the exact sheets, scales, and calculations they want.
  • Never start work on the strength of a submitted application. The permit is issued, not applied for, before you build.

Once you know your project needs a permit, the next question is the one that actually slows people down: what goes in the application? A building permit submission is mostly drawings and a couple of calculations that prove two things — that your project fits the lot (zoning) and that it's built safely (the building code). Get the package complete the first time and small-building permits often turn around in a couple of weeks; get it wrong and you join the large share of applications that get sent back for missing pieces.

Not sure you even need a permit, or which code applies? Start with the basics, then come back to assemble the package.
Do I Need a Permit? Codes & Authorities

The Core Documents

Most residential applications are built from the same short list. Names vary, but the intent is consistent across the country.

What It Looks Like by Project Type

ProjectUsually needsOften adds
DeckSite plan, plan view, cross-section (footings, ledger, guards/stairs)Beam/joist span details; engineered detail if outside prescriptive tables
Detached garage / shed (permit-size)Site plan with setbacks & coverage, floor plan, elevations, cross-sectionTruss drawings; electrical permit (separate)
AdditionSite plan, floor plans, elevations, cross-section, structural detailsLot grading/drainage plan; energy summary; engineer for structural ties
Interior reno / basementFloor plans (existing + proposed), structural details for any wall changesPlumbing/HVAC layout; beam design + engineer stamp if removing load-bearing walls
Rural entrance / culvertSite/location planRoad authority entrance permit; MDS/setback checks; separate from the building permit

For the size thresholds that decide whether each of these needs a permit at all, see Permits & Property Lines; for which code and authority governs in your province, see Building Permits & Codes in Canada.

Who Can Prepare the Drawings

This trips up homeowners who assume they can hire anyone — or no one:

Because the requirements are so local, the highest-value step is simply confirming, up front, exactly what your municipality will ask for — the required permits, the applicable setbacks, and the document checklist. A focused feasibility review of those questions before you design can save weeks of back-and-forth. Rules on who may prepare drawings vary by province and change over time — confirm with your provincial authority and, for anything structural, an engineer.

Why Packages Get Sent Back

Incomplete applications are the leading cause of permit delays — a large share of first submissions get returned for missing documents. The usual culprits:

✗ Deal-Breakers — Resolve Before You Apply

  • The project doesn't fit the zoning. If setbacks or lot coverage don't work, no drawing fixes it — you need a minor variance (slow, uncertain) first. The site plan will expose this, so check it before you invest in drawings.
  • Structural work with no engineer where one is required. Submitting unsized beams or an unsupported foundation just gets the package returned — and building it that way is a safety and liability problem.
  • You don't know your true property lines. The site plan is only as good as the survey under it. Guessed lines risk both rejection and a misplaced structure.
  • Treating the application as permission. Work started before the permit is issued can be ordered stopped, exposed for inspection, or removed.

The Safest Path Forward

  1. Get the municipality's application checklist — it lists the exact sheets, scales, and calculations they require for your project type.
  2. Confirm zoning first — setbacks, height, and lot coverage for your specific lot, before you design to them.
  3. Assemble the core package — site plan, floor plans, elevations, cross-section, and structural details, each to scale.
  4. Line up the supporting approvals — grading, septic, entrance/culvert, energy — that attach to your project.
  5. Get a professional for the parts that need one — an engineer for structural items, a registered designer where paid preparation requires it.
  6. Submit complete, in the format the city wants, and keep the issued permit and inspection records — they're resale assets.

Bottom Line

A building permit application is a small, predictable package: a site plan that proves the project fits the lot, drawings that show how it's built, and the calculations or approvals behind them. The thresholds and the exact checklist are local — so confirm what your municipality wants up front, assemble it complete, and you'll skip the most common reason permits stall. Start with whether you need one and which code applies.

Frequently Asked Questions

What documents do I need for a building permit in Canada?

Most residential applications need a completed form and fee, a scaled site plan showing setbacks and lot coverage, floor plans, exterior elevations, a cross-section, and structural details — plus supporting items like a grading plan, energy summary, or septic/entrance approval where they apply. The exact checklist is set by your municipality.

Can I draw my own plans for a building permit?

In most provinces a homeowner can prepare and submit drawings for their own home, taking responsibility for code compliance — but the drawings still must be clear, scaled, and complete. Drawings prepared for others for a fee typically must come from a registered designer or licensed professional (for example, a BCIN holder in Ontario).

Why do building permit applications get rejected?

Most often because they're incomplete: missing or unscaled drawings, no setback or lot-coverage information, structural elements with no sizing or required stamp, forgotten supporting approvals, or the wrong submission format. A large share of first submissions are returned for missing documents.

Do I need an engineer for a deck or garage permit?

Usually not, if the project stays within the building code's prescriptive span and footing tables. An engineer is required when you go beyond them — non-standard beams, load-bearing wall removals, or engineered foundations. Confirm with your building department, and consult an engineer for anything structural.

Disclaimer: This guide describes broad Canadian patterns for general information only. It is not legal or professional design advice, and required documents, thresholds, and who may prepare them vary by province and municipality and change over time. Always confirm the application checklist with your local building department, and consult an engineer for structural elements.